Template
RFQ Template for Custom Mechanical Parts and Assemblies
Every field a supplier needs to price your parts in one round, from the cover sheet to the line items, plus the email that sends it.
Free to copy and adapt · Updated November 17, 2026
A request for quote (RFQ) is the document that asks a supplier for a binding price and lead time on a design that is already decided. For custom mechanical parts, most quotes that come back late, padded or declined trace to the same gap: the package left a question the estimator had to guess at.
This template is built for hardware engineers and program managers sending machined, sheet metal, welded and other custom parts out for quote, whether one bracket or a full mechanical BOM. Copy the sections you need, fill in the brackets, and send the same package to every supplier so the quotes that come back can be compared line for line.
Simple RFQ template for a single part
For one well-defined part, a short request is enough, as long as the drawing carries the tolerances and finish. Make sure the email or quoting form note covers each of these:
Part number and revision (for example BRK-104, Rev B) Files attached: STEP model and PDF drawing, both at the same revision Material: grade and temper (for example 6061-T6 aluminum) Finish and secondary operations (for example Type II anodize, black, or as-machined) Quantity: the prototype quantity, plus a price break at the next quantity you expect to order General tolerance standard for undimensioned features (for example ISO 2768-m) Inspection and documents (for example a dimensional report on ballooned features and a material cert) Required ship date and ship-to city and country Date the quote is needed by
The full RFQ template
Use the full template for assemblies, multi-process BOMs, tight GD&T or any part with inspection or documentation requirements. Each line says what to write in that field.
1. Cover sheet
The first page tells the supplier who is asking, by when, and how to answer. Keep it to one page.
- RFQ number
- Your own reference (for example RFQ-2026-014). Ask suppliers to quote it on every reply.
- Issue date / quote due date
- The date you send the RFQ, and the date and time zone the quote is due.
- Buyer
- Company, name, role, email and phone of the person who receives the quote.
- Technical contact
- The engineer who can answer drawing questions the same day, with direct contact details.
- Confidentiality
- The NDA reference and date, or the terms the files are shared under.
- Quote validity requested
- How many days the price must hold.
- How to submit
- The email address or portal for replies, with the RFQ number in the subject line.
2. Scope and function
Two to four sentences of context change how an estimator reads every drawing that follows. Say what the parts do without disclosing more of the design than the quote needs.
- Project / assembly name
- The project or assembly name and the top-level assembly revision.
- What it does
- What the assembly does, what it mates with, the load or environment it sees, and the failure that must not happen.
- Build stage
- Prototype to prove a concept, pilot build, or production parts that must interchange with field units.
- Scope of this RFQ
- Parts only, parts plus finishing, or parts plus sub-assembly. List assembly operations (pressed bearings, inserts, bonded seals) with their acceptance criteria.
- Process route
- Fixed (say why), or open, so suppliers may propose another process and give the reason.
3. Files and revision control
Send the model and the drawing together, at the same revision. A conflict between them stops the quote until someone answers which one governs.
- 3D model
- A neutral format such as STEP AP214 or AP242, one file per part or one assembly file with part names matching the BOM.
- 2D drawing
- PDF with title block, revision, units, datums, GD&T, threads and surface finish callouts.
- BOM
- The BOM spreadsheet, with every line in the line-item table below.
- Reference material
- Photos, sketches or samples for parts with no drawing yet, such as springs or gaskets.
- Revision table
- Part number | Model file | Drawing file | Revision. Every row's model and drawing revisions must match.
- Which governs
- State whether the drawing or the model governs where they disagree.
4. Quality and inspection requirements
Inspection is part of the price. Anything added after the purchase order becomes a change order, so put it here.
- General tolerance
- The standard (for example ISO 2768-m) or title-block tolerances for dimensions not toleranced on the drawing.
- Critical features
- Balloon on the drawing the fits, bores, sealing faces and datums that govern function, and list them here.
- Inspection level
- Visual, a sample of critical dimensions, or full inspection of critical features, and the method expected (calipers, CMM or gauges).
- First article inspection
- Required on the first lot or not, and the report format: the supplier's own, or AS9102 forms if your program requires them.
- Documents with shipment
- Any of: certificate of conformance, material certs or mill test reports, finish or heat-treat certs, inspection report.
- Traceability
- None, to material heat lot, or to serial number with process records.
- Cosmetic standard
- Reference photos, a sample, or a written standard for which faces are cosmetic.
5. Quantities, delivery and commercial terms
Quantity changes the process and the tooling a supplier will propose, so give the whole volume picture, not only this order.
- Quantity tiers
- Prototype quantity, first production order and estimated annual usage. Ask for a price at each.
- Required ship date
- A date, or the lead time you need from PO. Say whether partial shipments are acceptable.
- Ship to
- Delivery address, shipping terms or Incoterm, and your carrier or account if you have one.
- Packaging and labeling
- For example individual bagging, part number labels and protection for finished faces.
- Substitutions
- No substitutions without written approval, or a list of approved alternates.
- Subcontracting
- Supplier must name any operation sent to a subcontractor and who remains accountable for it.
- Payment terms
- Your standard payment terms.
6. What the supplier must return
Ask for the same answers from every supplier, in the same order, so the quotes line up side by side.
- Price
- Unit price per line at each quantity tier, in the currency you name.
- Tooling and setup
- Tooling, fixtures and one-time setup (NRE) as separate lines, with who owns the tooling.
- Lead time
- Lead time per line from PO and drawing approval, in business days, and the date the full order ships.
- Material
- Whether the specified material is in stock or must be ordered, and its lead time if so.
- DFM feedback
- Any feature, tolerance or finish that drives cost or risk, and the change that would fix it.
- Exceptions
- Every requirement in this RFQ the quote does not meet, listed. No exceptions listed means none taken.
- In-house vs. outsourced
- Which operations are done in-house and which are subcontracted.
- Quote validity
- How long the price holds.
7. Line-item table
One row per unique part. This is the part of the RFQ that becomes the quote, so keep the columns the same for every supplier. Example values show the level of detail that prices in one round.
| Column | Example entry |
|---|---|
| Line | 3 |
| Part number / Rev | BRK-104 / B |
| Description | Motor mount bracket |
| Process | CNC milled |
| Material | 6061-T6 aluminum |
| Finish / secondary ops | Type II anodize, black; mask bore Ø22 |
| Critical features | Bore Ø22 H7; 4× M5 thread, position per drawing |
| Qty tiers | 10 / 100 / 1,000 per year |
| Docs required | Material cert; inspection report on ballooned features |
| Notes | Mates with line 5; no substitutions |
8. Process add-ons
Geometry alone does not price every process. Add the block for each process in your BOM; leave out the ones you don't need.
CNC machined parts
- Critical dimensions ballooned, with the fit or interface each one controls
- Thread form, size and class of fit (UN, metric or NPT; internal or external)
- Surface finish (Ra) on each functional face, not one value for the whole part
- Heat treatment, plating, anodize type and class, passivation, and what to mask
Sheet metal and weldments
- Material grade, temper and thickness, with the inside bend radius
- Weld type, size and location on the drawing; flatness or squareness after welding
- Hardware to insert (PEM or equivalent) by part number
- Coating color by RAL or Pantone code, gloss level, and every masked face or thread
Tube bending
- Outside diameter, wall thickness, material grade and temper
- Bend angles, centerline radius, and the distance and rotation between bends
- End work: trims, flares, swages, and weld preparation for fittings
- Prototype and expected production quantities, since both shape the tooling
Custom springs
- Spring type (compression, extension, torsion) and material
- Wire diameter, outside diameter, free length and end type
- Load at working height (or torque at working angle) and the margin you need
- Operating environment, cycle life, and what the spring seats against
Gaskets and seals
- Inside and outside dimensions, hole pattern and thickness
- Fluid or gas sealed, temperature range and pressure
- Surface finish of the mating face, cross-referenced to that part's drawing
- Bolt pattern, clamp load and the compression the gasket must take
Castings, molding and other tooled parts
- Quantities over the program's life, so tooling can be weighed against piece price
- Who owns the tool, and whether the price includes first-article samples
- Draft, parting line and gate location: fixed by you or left to the supplier
- Machining after casting or molding, with its own tolerances
RFQ email template
Send the package with a short email that says what is attached, when the quote is due, and who answers questions. This example is for a 12-part assembly; change the reference, part count and quantities to your own.
Subject: RFQ-2026-014: motor mount assembly, 12 parts, quote due Friday Hello, We'd like a quote for the 12 parts listed in the attached RFQ-2026-014 for our motor mount assembly. Attached: - RFQ document with requirements and line-item table - STEP models and PDF drawings (revisions match the revision table) - BOM Quantities: 10 sets now, 100 sets for the first production order, about 1,000 sets a year after that. We need the parts shipped by the date on the cover sheet, to the address there. Quotes are due by the date on the cover sheet. Please quote each line at each quantity, list tooling and setup separately, give lead time in business days from PO, and note any requirement you can't meet or any design change that would lower cost or risk. Our technical contact, named on the cover sheet, can answer drawing questions the same day. Thank you
Mistakes that send an RFQ back for a second round
Model and drawing at different revisions
The supplier has to stop and ask which one governs. Check the revision table before sending.
“Steel” or “aluminum” instead of a grade
Grade and temper change cost, machining, bending and welding. Name both.
Tight tolerances on every dimension
Blanket tight tolerances hide the features that matter and raise the price. Tolerance the critical features and let a general standard cover the rest.
Finish described in one word
“Powder coat” or “anodize” leaves color, type, thickness and masking open, and each supplier will price a different scope.
Inspection added after the order
A first article report or material certs asked for after the PO becomes a change order. Put them in section 4.
Only the prototype quantity
Without the production volume, a supplier can't tell whether tooling or a different process would pay off.
Frequently asked questions
What is an RFQ template?
An RFQ template is a reusable request-for-quote document with the fields a supplier needs to price a part: files, material, finish, quantities, inspection, delivery and the format of the answer. Filling in the same template for every supplier makes their quotes comparable.
What is the difference between an RFQ, an RFP and an RFI?
An RFQ asks for a price and lead time on a design that is already decided. An RFP asks suppliers to propose how they would solve an open problem. An RFI gathers information about suppliers' capabilities before you are ready to ask for either.
Is a CAD upload to an online quoting tool enough?
For a single, well-defined part whose drawing carries the tolerances and finish, often yes. For assemblies, tight GD&T, specific inspection requirements, weldments or specialty processes, send a full RFQ so the supplier can stand behind the price.
How many suppliers should get the same RFQ?
Enough to compare price, lead time and engagement, and few enough that you can answer every supplier's questions before the due date. Send each one the identical package so the answers line up.
How long should suppliers get to respond?
It depends on the number of parts and processes and on how busy your suppliers are. Ask your shortlisted suppliers what turnaround they need for a package of this size, then put a firm due date on the cover sheet.
Go deeper
- What Your RFQ Must Include to Price a Multi-Process Assembly in One Round
- How to Write an RFQ That Forces a Supplier to Engage With a Complex Geometry Instead of Declining It
- Uploading a CAD File for a Quote Versus Submitting a Full RFQ Package
- BOM Readiness Checklist Before Sending RFQs
- Why Complex Machined Parts Stall at the RFQ Stage and How to Move Them Forward